Since the commencement of Hubei runye Yichang Industrial Park project on November 10, 2016, after more than two years of construction and strong support from relevant leaders of government departments, the industrial park of the base has been completed and entered the final commissioning stage. The company will put into production on June 1, 2019.
Yichang Industrial Park covers an area of 100 mu, with an investment of 200 million yuan. The project plans 18 automatic aluminum shell stretching production lines, 9 ultrasonic full-automatic cleaning lines, and 20 automatic cover plate assembly lines. It is estimated that the monthly production capacity will reach 10.8 million sets.